.jpeg)
The Isle House team officially achieved temporary certificate of occupancy (TCO) on June 7.
The Isle House team officially achieved temporary certificate of occupancy (TCO) on June 7.
At the beginning of the year, Sr. Superintendent Maria Damas, who oversaw the TCO schedule with the project team's support, set a goal of June 7 to reach the milestone. She hit that date precisely. "A lot of things had to go perfectly to achieve that," says Project Director Ted Williams.
Ted shouted out other team members for their contributions:
The project will reach substantial completion in mid-July, with the first residents arriving on August 1.
What they're saying: "This TCO doesn't happen without the extraordinary hard work of each and every one of our One Webcor team members," Ted says. These include: Maria Damas, Karen Turcios, Kristina Reyna, Cynthia Zolezzi, Lynn Bass, John Wilson, Pat Forbeck, Kenny Hua, Matt Moran, Kelly Martz, Justin Schmitt, Lucas Decasper, Ivan Chavez, Phil Nunez, BRENNAN TAYLOR, David Grattan, Mark Zherebnenkov, Erik Roggeveen, Rene Iriartborde, Tom McCue, Ivan Ramos, Jorge "Nacho" Equihua, Mario Saldana, Sergio Ruiz (and shout out to those that joined us for a portion of the project: Dave Thompson, Jocelyn Mezofenyi, Stephanie Azzolino, Erik Biczkow, Paulo "Porky" Munoz, Brian Kearney, Karl Jeppesen, Jan Yi, Jackie Cardera, Zak McKellips, and Mac Hammitt).

Building 600, one of four buildings comprising the Biosolids Digester Facilities Project (BDFP), topped out recently, marking the completion of most of the concrete structure.
Building 600, one of four buildings comprising the Biosolids Digester Facilities Project (BDFP), topped out recently, marking the completion of most of the concrete structure.
Why it matters: Building 600's unique design and construction challenges stand out from the other BDFP structures.
The team poured the last perimeter wall on May 21. While the metal deck and steel erection will continue into early July, the significance of this date was not lost on the team despite a planned reduction in crew size in the coming weeks.
Go deeper: The "tour route" observation area is a noteworthy feature of Building 600. This corridor allows visitors to view the processing activities from above, offering a glimpse into the project's operations from each floor. The architect deemed these areas to require a higher quality of finish. They were treated with the same care and attention as the building's exterior architectural concrete, ensuring a polished and professional look.

Zoom in: One of the most complex coordination efforts involved the installation of three 63,000-pound hoppers on the level one slab. These massive pieces of machinery, essential for the project's operations, required 18 months of meticulous planning.
The project began under challenging conditions, with late changes to the mat foundation and continuous rain during the foundation pours. The team had to adapt, working staggered shifts and starting early to avoid the heaviest downpours. Despite these obstacles, they managed to pour the 150,000 square feet of walls and complete the structure, maintaining a steady workflow and keeping the project on schedule.
"It sucks to deal with rain, and it can suck to have people work in the rain, but it also sucks to have to reschedule pours," Daniel said. "We found a good balance for managing work during the rain cycles. Most days, it doesn't rain for 12 full hours, so you find the right balance, doing other work during the downpours."
The backstory: Concrete work for the project began 18 months ago, with foundation work starting in December 2022. As the project progresses, the team remains focused on maintaining the high standards and quality that have characterized their work.
The team held a barbecue prepared by the Webcor Craft barbeque team to celebrate the topping out. About 350 people attended. The event featured a few speeches recognizing the efforts and contributions of everyone involved.


The UCSF New Hospital at Parnassus Heights (NHPH) team installed oxygen tanks without disrupting the flow of oxygen to the existing hospital.
Why it matters: The UCSF New Hospital at Parnassus Heights (NHPH) team installed oxygen tanks without disrupting the flow of oxygen to the existing hospital. When activated, the tanks will supply oxygen to both the existing and new hospitals.
The big picture: The installation site on Mt. Sutro required significant preparation. Superintendent Saleh Fadhel said the team had to shave part of the hill and build a massive shoring and retaining wall.
Given the complexity and size of the tanks � one 9,000-gallon tank and two 11,000-gallon tanks, each nine feet in diameter and 35 feet tall � logistics played a crucial role.
The tanks were installed on piles with anchor bolts about 12 feet long, embedded in 40-foot-deep piles. "Each tank has three legs, and each leg sits on a pile with four anchors," Saleh described. Despite facing challenges with alignment, the team successfully installed the tanks by the end of the day.
Go deeper: The installation was a collaborative effort involving multiple parties, including the contractor's team, owners' representatives, subcontractors, and specialists.
The team worked together to make on-site modifications, ensuring the tanks were installed correctly. "It was mind-boggling and awesome at the same time to see everyone come together to meet the deadline," Saleh remarked.
Next Steps: With the tanks in place, the project is moving into the testing and commissioning phase. The oxygen tanks, complete with vaporizers that convert liquid oxygen to gas, will soon be operational, ensuring a reliable oxygen supply to the existing and new hospitals.